15A NCAC 13B .0535       APPLICATION REQUIREMENTS FOR C&DLF FACILITIES

(a)  Permit for a new facility. In accordance with Rule .0201 of this Section the permit for a new C&DLF facility shall have two parts: 

(1)           Permit to Construct.  The owner and operator of a new facility must meet the requirements of Rule .0536 of this Section prior to submitting an application for a permit to construct. A complete application for a permit to construct must contain the following:

(A)          a facility plan that describes the comprehensive development of the C&DLF facility prepared in accordance with Rule .0537 of this Section;

(B)          an engineering plan for the initial phase of landfill development prepared in accordance with Rule .0539 of this Section;

(C)          a construction quality assurance plan prepared in accordance with Rule .0541 of this Section;

(D)          an operation plan prepared in accordance with Rule .0542 of this Section;

(E)           a closure and post-closure plan prepared in accordance with Rule .0543 of this Section; and

(F)           monitoring plans prepared in accordance with Paragraph (a) of Rule .0544 of this Section.

(2)           Permit to Operate. The owner and operator must meet the pre-operative requirements of the permit to construct in order to qualify the constructed C&DLF unit for a permit to operate. Construction documentation must be submitted in a timely and organized manner in order to facilitate the Division's review.

(b)  Amendment to the permit. A complete application for an amendment to the permit must contain:

(1)           an updated engineering plan prepared in accordance with Rule .0539 of this Section;

(2)           an updated construction quality assurance plan prepared in accordance with Rule .0541 of this Section;

(3)           an updated operation plan prepared in accordance with Rule .0542 of this Section;

(4)           an updated closure and post-closure plan prepared in accordance with Rule .0543 of this Section; and

(5)           an updated monitoring plan prepared in accordance with Rule .0544 of this Section.

(c)  Substantial amendment to the permit.  A complete application for a substantial amendment to the permit must contain:

(1)           a facility plan that describes the comprehensive development of the C&DLF facility prepared in accordance with Rule .0537 of this Section; and

(2)           local government approval in accordance with Subparagraph (c)(11) of Rule .0536 of this Section.

(d)  Modifications to the permit. The owner or operator may propose to modify plans that were prepared and approved in accordance with the requirements set forth in this Section.  A complete application must identify the requirement(s) proposed for modification and provide sufficient information in order to demonstrate compliance with the applicable requirements of this Section.

 

History Note:        Authority G.S. 130A-294;

Eff. January 1, 2007.